JABER AL-AHMAD CITY INFRASTRUCTURE WORKS, BLOCKS N

  • image LOCATION Jaber Al Ahmed City
  • image CLIENT Public Authority of Housing Works
  • image CONTRACT VALUE KD. 55 M (US$ 182 M)
  • image Construction Period 2010-2013 (32 months)
  • DESCRIPTION

    Infrastructure work for 2659 plots covering an area of 3,281,000 m² which includes all Underground pipe works, Power Conduits, Telephone Cable Conduits, Street lighting works. Construction of 101 precast for substation buildings in the area.

  • KEY FEATURES

    Water Supply, Storm WATER & Sanitary line for 197 km Road works Asphalt Kerbstone & Road marking for an area of 725,000 m² Soil improvement of the area by Dynamic Compaction 3,281,000 m² Supply & transportation of Backfilling Material 15,000,000 m³ Compaction of Backfilled Soil 8,000,000 m³

CONTACT

Moharafat General Contracting Company
Shuwaikh Industrial Area 3,
Block-B, Street 31, Building Number 255,
P . O. Box 2130 Safat, Kuwait.

Tel : +965 2292 9868
E-Mail : sales@moharafatcontractingco.com

ISO Certificate.

image